Purpose: Provide a detailed, actionable implementation plan for deploying the Community Impact Visibility Platform at Sepfluor, from pilot through production and Mining Indaba 2026 award submission readiness.


OptionDurationScopeInvestmentRecommended Start
Pilot: SLP Compliance & Impact Visibility8-10 weeksNokeng mine, SLP dashboards, Mining Indaba submission builderR550K-R750KJanuary 2025 (Mining Indaba deadline: Sept 2025)
Production: Full Recognition Platform12-16 weeksAll SLP programs, GRI 14 compliance, multi-award supportR1.5M-R2MQ2 2025 (post-pilot validation)
Strategic Partnership: Multi-Site Expansion24-36 monthsWiltin + Wallmannsthal, innovation, industry leadershipR2.5M-R4.5M2026-2027 (post-production success)

Recommended Path: Start with Pilot in January 2025 → Deliver by April 2025 → Mining Indaba submission September 2025 → Expand to Production Q3 2025.


Critical Timeline Constraint: Mining Indaba 2026

Section titled “Critical Timeline Constraint: Mining Indaba 2026”

Mining Indaba Responsible Resourcing Awards Timeline:

  • Submissions Open: June 2025 (estimated - 7 months from now)
  • Submission Deadline: September 2025 (10 months from now)
  • Awards Ceremony: February 2026 (15 months from now)

Impact on Decision:

  • Start January 2025: Pilot complete by April 2025 → 5 months to refine submission → strong award candidacy
  • Start March 2025: Pilot complete by June 2025 → 3 months to refine submission → weaker evidence base
  • Start May 2025: Pilot complete by August 2025 → 1 month to submit → rushed submission, low win probability
  • Delay past May 2025: Miss Mining Indaba 2026 entirely → earliest opportunity is 2027 (2-year delay)

Recommendation: Start pilot by end of January 2025 at latest to maximize Mining Indaba 2026 award potential.


Pilot: Community Impact Visibility (8-10 Weeks)

Section titled “Pilot: Community Impact Visibility (8-10 Weeks)”

Objective: Transform Sepfluor’s SLP compliance data into compelling impact stories that reduce DMRE reporting burden by 70%, achieve Mining Indaba 2026 submission readiness, and build foundation for industry recognition.

Scope:

  • SLP compliance dashboard (5 focus areas: Community Development, Skills, Equity, LED, Welfare)
  • Budget tracking vs. DMRE targets (5% wage skills, 2-3% EBITDA LED)
  • Impact storytelling hub (beneficiary tracking, project galleries, success stories)
  • Mining Indaba 2026 submission builder (Community Engagement Award focus)
  • Public-facing impact portal (community.sepfluor.co.za)
  • Stakeholder communication templates (community newsletters, investor briefings, DMRE reports)
  • Nokeng mine site only (expand to Wiltin/Wallmannsthal in Phase 2)

Success Criteria:

  • 70%+ time savings on SLP compliance reporting (from 30 hrs/month to <10 hrs/month)
  • 100% DMRE audit trail completeness
  • 1 Mining Indaba award submission completed (Community Engagement Award 90%+ complete)
  • 4+ stakeholder communication packages published (community, investors, employees, DMRE)
  • Sub-3-second dashboard load times
  • 90%+ positive stakeholder feedback on transparency

Week 1: Project Kickoff & Mining SLP Discovery

Section titled “Week 1: Project Kickoff & Mining SLP Discovery”

Objectives:

  • Align stakeholders on scope, timeline, success criteria, and Mining Indaba goals
  • Map SLP data sources (existing spreadsheets, PDFs, shared drives, photos)
  • Understand Nokeng mine operations and community catchment area
  • Identify risks and mitigation strategies

Deliverables:

  • Project charter signed
  • SLP data source inventory (2023-2024 records, evidence files)
  • Integration approach confirmed (initial: standalone, future: HR/ERP integration)
  • Mining Indaba award category selection (primary: Community Engagement)
  • Risk register created
  • Communication plan established

Activities:

DayActivityiSu TeamSepfluor Team
Day 1Kickoff meeting - Align on scope, timeline, Mining Indaba goalsProject Manager, Technical LeadCEO/Chairman, Community Relations Lead, ESG/Sustainability Manager
Day 2SLP data inventory - Map all compliance data sources (spreadsheets, PDFs, photos, agreements)Data EngineerCommunity Relations team, HR (skills development records)
Day 3Nokeng mine visit - Understand operations, community context, key projectsProject Manager, Technical LeadCommunity Relations, Operations (site tour)
Day 4Mining Indaba planning - Review past winners, identify Sepfluor strengths, draft award positioningProject ManagerCommunity Relations, CEO/Chairman (strategy)
Day 5Risk assessment & stakeholder mapping - Identify blockers, secure commitmentsProject ManagerExecutive sponsor (CEO/Chairman)

Key Meetings:

  • Kickoff meeting (3 hours) - All stakeholders, site context, strategic alignment
  • SLP data workshop (4 hours) - Community Relations team, document all data sources
  • Mining Indaba strategy session (2 hours) - CEO/Chairman, award positioning
  • Executive briefing (1 hour) - CEO/Chairman, confirm budget/timeline/commitments

Milestone: Project charter approved, SLP data sources documented, Mining Indaba award category selected (Community Engagement primary, Labour secondary).


Week 2: Data Migration & SLP Record Digitization

Section titled “Week 2: Data Migration & SLP Record Digitization”

Objectives:

  • Import existing SLP data (2023-2024 compliance records)
  • Digitize historical community consultation records
  • Index evidence files (photos, agreements, certificates, impact assessments)
  • Set up development and staging environments

Deliverables:

  • 2023-2024 SLP data imported (beneficiaries, projects, training programs, suppliers)
  • Community consultation records digitized
  • Evidence library indexed (1,247+ files tagged and searchable)
  • Database schema designed (beneficiary tracking, SLP compliance, budgets)
  • Development environment configured

Activities:

DayActivityiSu TeamSepfluor Team
Day 1-2Historical data import - Import 2023-2024 SLP records from Excel/PDFsData EngineerCommunity Relations (provide data files, validation)
Day 3Beneficiary database setup - Import beneficiary lists (2,340+ served)Data EngineerCommunity Relations (beneficiary records, anonymization guidance)
Day 4Evidence file indexing - Tag and categorize 1,247+ files (photos, agreements, certificates)Data Engineer, Backend DeveloperCommunity Relations (file access, metadata guidance)
Day 5Data validation - Verify accuracy, identify gaps, flag missing evidenceData EngineerCommunity Relations (spot checks, gap identification)

Technical Tasks:

  • Configure PostgreSQL database with mining SLP schema
  • Build data import scripts (Excel, CSV, PDF extraction)
  • Implement evidence file storage and indexing (GIS metadata for project locations)
  • Set up Redis caching layer
  • Configure development and staging environments (Railway.app, Hetzner Cape Town)

Milestone: Historical SLP data migrated, beneficiary database populated, evidence library indexed and searchable.


Week 3: SLP Compliance Dashboard Development

Section titled “Week 3: SLP Compliance Dashboard Development”

Objectives:

  • Build core SLP compliance dashboard (5 focus areas)
  • Implement budget tracking vs. DMRE targets
  • Create real-time KPI cards with trend indicators
  • Build Nokeng mine-site view

Deliverables:

  • SLP compliance dashboard (MVP) with 5 focus areas
  • Budget tracking dashboards (5% wage skills, 2-3% EBITDA LED)
  • KPI cards (beneficiaries served, jobs created, investment totals, compliance status)
  • Nokeng mine-site configuration (geographic boundaries, community mapping)
  • DMRE audit readiness indicators

Activities:

DayActivityiSu TeamSepfluor Team
Day 1-2Dashboard UI framework - Navigation, layout, Sepfluor brandingFrontend DeveloperMarketing/Brand (logo, colors, brand guidelines)
Day 3-4SLP focus area dashboards - Community Dev, Skills, Equity, LED, WelfareFrontend Developer, Backend DeveloperCommunity Relations (metric definitions, target validation)
Day 5Budget compliance tracking - 5% wage, 2-3% EBITDA, forecast year-end performanceFrontend Developer, Backend DeveloperFinance/Accounting (budget data), Community Relations (allocation)

Technical Tasks:

  • Build Next.js dashboard pages (5 focus areas)
  • Implement FastAPI endpoints for SLP metrics
  • Create Recharts visualizations (line charts, bar charts, KPI cards)
  • Build mine-site filtering logic (Nokeng only for pilot)
  • Apply Sepfluor branding (colors, logo, fonts)
  • Implement GIS integration for project mapping

Milestone: SLP compliance dashboard visible with real Nokeng data, budget tracking operational.


Week 4: Impact Storytelling Hub & Public Portal

Section titled “Week 4: Impact Storytelling Hub & Public Portal”

Objectives:

  • Build public-facing impact portal (community.sepfluor.co.za)
  • Create beneficiary tracking system (2,340+ beneficiaries)
  • Develop success story templates and curation tools
  • Implement multi-language support (English, Ndebele, Sepedi)

Deliverables:

  • Public impact portal (community.sepfluor.co.za subdomain or standalone)
  • Interactive GIS map with project markers (education, infrastructure, healthcare, LED)
  • Beneficiary impact dashboard (real-time counters, trend visualizations)
  • Success story showcase (3-5 stories curated)
  • Multi-media evidence library (photos, videos, documents searchable)
  • Multi-language support (English, Ndebele, Sepedi auto-translation)

Activities:

DayActivityiSu TeamSepfluor Team
Day 1Public portal framework - Homepage, navigation, accessibility designFrontend DeveloperCommunity Relations (community needs, accessibility requirements)
Day 2GIS project mapping - Interactive map with project markers (blue: education, green: infrastructure, orange: healthcare, purple: LED)Frontend Developer, Backend DeveloperCommunity Relations (project GPS coordinates, community boundaries)
Day 3Beneficiary dashboard - Real-time counters (2,340 served, jobs created, investment totals)Frontend DeveloperCommunity Relations (beneficiary data validation)
Day 4Success story curation - Template-driven story builder, photo gallery, testimonial captureFrontend Developer, Backend DeveloperCommunity Relations (identify 3-5 compelling stories)
Day 5Multi-language support - Auto-translation (English, Ndebele, Sepedi), low-bandwidth designFrontend DeveloperCommunity Relations (translation validation)

Technical Tasks:

  • Build public portal Next.js pages
  • Implement GIS mapping (Leaflet or Mapbox)
  • Create beneficiary story templates (skills development, community projects, LED suppliers)
  • Build photo gallery with before/after comparison features
  • Implement multi-language auto-translation
  • Configure low-bandwidth design for community access (limited connectivity)

Milestone: Phase 1 Complete - SLP dashboards built, public portal live, beneficiary tracking operational, ready for stakeholder review.


Week 5: Phase 1 Stakeholder Review & Feedback

Section titled “Week 5: Phase 1 Stakeholder Review & Feedback”

Objectives:

  • Present Phase 1 deliverables to stakeholders (CEO, Chairman, Community Relations, Board if available)
  • Gather feedback on dashboards, public portal, beneficiary tracking, usability
  • Prioritize feedback for Phase 2 adjustments
  • Validate Mining Indaba award positioning

Deliverables:

  • Stakeholder demo completed (CEO, Chairman, Community Relations, Operations)
  • Feedback documented and prioritized
  • Phase 2 adjustments scoped
  • Mining Indaba award category validation (Community Engagement confirmed or adjusted)

Activities:

DayActivityiSu TeamSepfluor Team
Day 1Stakeholder demo - Present SLP dashboards, public portal, beneficiary tracking, Mining Indaba positioningProject Manager, Technical LeadCEO (Hendrik Snyman), Chairman (Dr. Lelau Mohuba), Community Relations Lead, ESG Manager
Day 2Feedback consolidation - Document all feedback, clarify requirementsProject ManagerCommunity Relations (clarifications), CEO/Chairman (strategic direction)
Day 3Mining Indaba positioning workshop - Validate award category, identify story gaps, plan evidence collectionProject ManagerCEO/Chairman, Community Relations (award strategy)
Day 4-5Phase 2 planning - Adjust scope based on feedback, finalize Mining Indaba submission timelineTechnical LeadExecutive sponsor (CEO/Chairman approval)

Key Meetings:

  • Stakeholder demo (3 hours) - All senior stakeholders, board members if available
  • Mining Indaba positioning workshop (2 hours) - CEO/Chairman, Community Relations, award strategy
  • Feedback workshop (2 hours) - Community Relations team, prioritize adjustments
  • Phase 2 planning (1 hour) - Project leads, finalize scope

Milestone: 40% Milestone Payment - Phase 1 complete, stakeholder-approved, Phase 2 scoped, Mining Indaba category validated.


Week 6: Mining Indaba Submission Builder & Automation

Section titled “Week 6: Mining Indaba Submission Builder & Automation”

Objectives:

  • Build Mining Indaba award submission builder (DocsHub module)
  • Create DMRE automated reporting
  • Develop stakeholder communication templates
  • Implement authentication and role-based access control

Deliverables:

  • Mining Indaba submission builder (Community Engagement Award template pre-populated)
  • DMRE annual compliance report automation (one-click PDF generation)
  • Stakeholder communication templates (5 audiences: community, investors, employees, municipalities, DMRE)
  • User authentication (login, session management)
  • Role-based access (Admin, Analyst, Executive, Public)

Activities:

DayActivityiSu TeamSepfluor Team
Day 1-2Mining Indaba submission builder - Template structure (executive summary, beneficiary impact, partnerships, evidence appendices)Backend Developer, Frontend DeveloperCommunity Relations (past Mining Indaba submissions for reference, if available)
Day 3DMRE report automation - Annual compliance report (5 focus areas, budget tracking, evidence appendices)Backend DeveloperCommunity Relations (DMRE report requirements, past submissions)
Day 4Stakeholder communication templates - Community newsletters, investor briefings, employee impact, municipality IDP alignmentBackend Developer, Frontend DeveloperCommunity Relations (stakeholder communication needs)
Day 5Authentication & authorization - User roles (Admin, Analyst, Executive, Public), login system, permissionsBackend DeveloperIT/Security (requirements if applicable)

Technical Tasks:

  • Implement ReportLab PDF generation for Mining Indaba submissions
  • Create Mining Indaba award templates (Community Engagement, Labour, Transparency)
  • Build “Export Award Submission” UI buttons (one-click 25-page PDF generation)
  • Implement DMRE compliance report generator
  • Create stakeholder communication templates (auto-populated with platform data)
  • Build session-based authentication with role-based access control

Milestone: One-click Mining Indaba submission generation working, DMRE report automation functional, stakeholder communication templates ready.


Week 7: GRI 14 Compliance & Advanced Features

Section titled “Week 7: GRI 14 Compliance & Advanced Features”

Objectives:

  • Build GRI 14: Mining Sector 2024 compliance dashboard (pilot scope: 8-10 material topics)
  • Implement mine-site level transparency (Nokeng detailed reporting)
  • Add risk monitoring and automated alerts (SLP compliance gaps, consultation overdue, budget variances)
  • Optimize dashboard performance

Deliverables:

  • GRI 14 compliance dashboard (pilot scope: 8-10 high-priority material topics)
  • Nokeng mine-site transparency view (GRI 14 site-level reporting)
  • Risk monitoring dashboards (SLP compliance gaps, consultation delays, budget variances)
  • Automated alerts (email/SMS notifications for critical issues)
  • Performance optimization complete (<3 second load times)

Activities:

DayActivityiSu TeamSepfluor Team
Day 1-2GRI 14 dashboard - 8-10 priority material topics (community engagement, water, emissions, local economic impacts, etc.)Frontend Developer, Backend DeveloperESG Manager (GRI 14 priority topics for Sepfluor, data availability)
Day 3Nokeng mine-site transparency - Site-level GRI 14 reporting (required for standard compliance)Frontend DeveloperOperations (site-specific data), Community Relations
Day 4Risk monitoring & alerts - SLP gaps, consultation overdue, budget variance warningsBackend DeveloperCommunity Relations (alert thresholds, notification preferences)
Day 5Performance optimization - Database indexing, caching, query optimizationBackend DeveloperN/A

Technical Tasks:

  • Build GRI 14 compliance dashboard pages (8-10 material topics for pilot)
  • Implement mine-site level filtering (Nokeng-specific data)
  • Create risk monitoring algorithms (gap detection, deadline tracking, budget variance)
  • Build automated email/SMS alert system
  • Implement database indexes for performance
  • Optimize Redis caching strategies

Milestone: GRI 14 pilot dashboard operational, risk monitoring active, performance targets met (<3 second load).


Objectives:

  • Conduct comprehensive testing with Sepfluor users (Community Relations, ESG Manager, CEO/Chairman)
  • Identify and fix bugs, usability issues
  • Validate success criteria achievement
  • Test Mining Indaba submission generation (end-to-end workflow)

Deliverables:

  • UAT test plan executed
  • Bug fixes completed
  • Performance validated
  • Success criteria verified
  • Mining Indaba submission quality validated

Activities:

DayActivityiSu TeamSepfluor Team
Day 1UAT kickoff - Distribute test plan, train testers, explain success criteriaProject Manager, QACommunity Relations Lead, ESG Manager, CEO/Chairman
Day 2-3Testing execution - Users test all features (dashboards, public portal, Mining Indaba builder, DMRE reports), log issuesQA (support)Community Relations (primary testers), ESG Manager, CEO/Chairman (executive dashboards)
Day 4Bug fixes - Address critical and high-priority issues identified during UATDevelopersN/A
Day 5Regression testing - Verify fixes, retest critical paths, validate Mining Indaba submission qualityQACommunity Relations (verification)

Test Scenarios:

  • Dashboard load times (<3 seconds for SLP compliance dashboard)
  • Data accuracy (compare platform data to source spreadsheets/PDFs)
  • Filtering functionality (focus area selection, time periods, budget tracking)
  • Mining Indaba submission generation (one-click PDF, 25-page output, evidence compilation)
  • DMRE report generation (one-click compliance report, evidence bundle)
  • Public portal accessibility (mobile access, multi-language support)
  • Authentication (login, permissions, session management)
  • Risk alerts (SLP gap notifications, consultation reminders)

Milestone: All critical bugs fixed, success criteria validated, UAT sign-off from CEO/Chairman.


Objectives:

  • Train all user groups (administrators, community relations team, executives)
  • Provide comprehensive documentation (user manuals, video tutorials)
  • Establish support procedures
  • Conduct final Mining Indaba submission review

Deliverables:

  • Training sessions completed (3 sessions: Admin, Community Relations, Executives)
  • User manuals (Admin, Analyst/Community Relations, Executive)
  • Technical documentation (architecture, data schema, API docs)
  • Quick-start guides and video tutorials (5-10 minutes each)
  • Support procedures established (email, video call)
  • Mining Indaba submission draft reviewed and refined

Activities:

DayActivityiSu TeamSepfluor Team
Day 1Admin training - System configuration, user management, data entry workflows, evidence file managementTechnical LeadIT administrators, Community Relations (data owners)
Day 2Community Relations training - Dashboard usage, beneficiary tracking, project logging, Mining Indaba submission builder, DMRE report generationProject ManagerCommunity Relations team (primary users)
Day 3Executive training - Executive dashboards, public portal navigation, Mining Indaba submission review, stakeholder communicationProject ManagerCEO (Hendrik Snyman), Chairman (Dr. Lelau Mohuba), ESG Manager
Day 4Mining Indaba submission review - Review generated Community Engagement Award submission, refine stories, verify evidence completenessProject Manager, Technical LeadCEO/Chairman, Community Relations (submission quality validation)
Day 5Documentation finalization & support handover - Finalize user manuals, video tutorials, FAQs, establish support channelsTechnical Writer, Project ManagerIT support team (if applicable)

Training Materials:

  • User manuals (PDF, web-based)
    • Administrator manual (system config, user management)
    • Community Relations manual (daily workflows, data entry, reporting)
    • Executive manual (dashboard navigation, award submissions, strategic insights)
  • Video tutorials (5-10 minutes each)
    • How to log SLP activities
    • How to generate Mining Indaba submission
    • How to generate DMRE compliance report
    • How to update public portal content
    • How to track beneficiaries
  • Quick-start guides (1-page cheat sheets)
  • FAQ document
  • Support contact information

Milestone: All users trained, documentation delivered, support procedures established, Mining Indaba submission draft reviewed and approved.


Objectives:

  • Deploy to production environment
  • Conduct final validation
  • Launch platform to all stakeholders
  • Complete project handover
  • Initiate 30-day support period

Deliverables:

  • Production deployment complete (Railway.app, Hetzner Cape Town hosting)
  • Public portal live (community.sepfluor.co.za)
  • Launch communication sent (internal announcement, community newsletter, investor briefing)
  • Project handover complete (documentation, credentials, support procedures)
  • 30-day support period initiated

Activities:

DayActivityiSu TeamSepfluor Team
Day 1Production deployment - Deploy to production environment (Railway.app, Hetzner Cape Town)DevOps, Backend DeveloperIT team (environment access, DNS configuration for community.sepfluor.co.za)
Day 2Production validation - Smoke testing, data verification, performance validationQACommunity Relations (spot checks), ESG Manager (validation)
Day 3Launch communication - Internal announcement, community newsletter, investor briefing, public portal announcementProject ManagerCommunications/HR (internal), Community Relations (external)
Day 4Go-live support - Monitor system, address user questions, troubleshoot issuesAllCommunity Relations (first users), CEO/Chairman (executive access)
Day 5Project handover - Deliverable sign-off, lessons learned, next steps (production expansion, Mining Indaba submission refinement)Project ManagerCEO/Chairman, Project sponsor

Launch Activities:

  • Deploy to production infrastructure (Railway.app, Hetzner Cape Town data residency)
  • Configure production data connections
  • Distribute user credentials (Admin, Community Relations, Executives)
  • Send launch announcement (internal: employees, external: communities, investors)
  • Publish public portal (community.sepfluor.co.za)
  • Monitor system performance (uptime, load times, errors)
  • Address initial user questions and support requests

Milestone: Project Complete - 30% final milestone payment, 30-day support period begins, public portal live.


Duration: Days 1-30 after launch

Scope:

  • Bug fixes and issue resolution
  • User questions and support (Community Relations, ESG Manager, CEO/Chairman)
  • Performance monitoring (dashboard load times, uptime)
  • Minor adjustments based on feedback
  • Mining Indaba submission refinement support (February-September 2025)
  • Quarterly check-in scheduling

Support Channels:

  • Email: support@isutech.co.za
  • Response time: 4-24 hours depending on severity
  • Video calls: As needed for complex issues (Mining Indaba submission refinement, dashboard customization)

Severity Levels:

  • Critical (System Down): 30-minute response, 4-hour resolution target
  • High (Feature Broken): 2-hour response, 24-hour resolution target
  • Medium (Usability Issue): 4-hour response, 48-hour resolution target
  • Low (Enhancement Request): 1-business-day response, quarterly release cycle

Exclusions (Requires Change Order):

  • New features or modules (e.g., Skills Development tracking beyond pilot scope)
  • Additional mine sites (Wiltin, Wallmannsthal - production phase)
  • Integration with new data sources (HR systems, ERP - production phase)
  • Major redesign or restructuring
  • Additional Mining Indaba award categories beyond Community Engagement (Labour, Transparency - production phase)

Mining Indaba Submission Refinement (Post-Pilot):

  • April-June 2025: Accumulate additional platform data (3 more months of beneficiary tracking, project evidence)
  • July-August 2025: Refine Community Engagement Award submission (incorporate 6-9 months of platform data)
  • September 2025: Final submission review and submit before deadline
  • Support Included: iSu Technologies provides ongoing Mining Indaba submission refinement support during 30-day period and beyond (quarterly check-ins)

Production: Full Recognition Platform (12-16 Weeks)

Section titled “Production: Full Recognition Platform (12-16 Weeks)”

Trigger: Successful pilot with demonstrated ROI (70% time savings validated) and stakeholder buy-in

Scope Expansion from Pilot:

  1. Skills Development Tracking - Learnership management, bursary administration, training programs, 5% wage compliance
  2. Local Economic Development Intelligence - Supplier management (34+ suppliers), procurement analytics, job creation tracking
  3. GRI 14 Full Compliance - 25 material topics (vs. 8-10 in pilot), comprehensive mining sector standard
  4. Multi-Award Submission Support - Mining Indaba (3 categories), EY Excellence, JSE SRI, MSCI ESG
  5. Employee Welfare Monitoring - Safety performance (LTI rates), health programs, wellbeing initiatives
  6. Multi-Stakeholder Portal Access - Community, employee, municipality, union, investor portals (role-based access)
  7. Advanced Impact Analytics - ML-powered risk prediction, beneficiary impact modeling, benchmark dashboards

Month 1: Production Planning & Skills Development Tracking

Section titled “Month 1: Production Planning & Skills Development Tracking”

Week 1-2: Production Planning & Pilot Optimization

  • Review pilot lessons learned (what worked, what didn’t, user feedback)
  • Optimize SLP dashboards based on 8-10 weeks of usage data
  • Plan Skills Development module (learnership tracking, bursary administration)
  • Expand team if needed (additional developer for production scale)

Week 3-4: Skills Development Tracking System

  • Build learnership management (application, enrollment, tracking, certification)
  • Implement bursary administration (applications, approvals, payments, academic tracking)
  • Create training program tracking (courses, completions, hours, budget)
  • Build 5% wage spend target automation (real-time compliance monitoring)
  • Implement certification repository (N4, N5, artisan qualifications, safety tickets)

Deliverables:

  • Optimized SLP compliance dashboards
  • Skills development tracking system (learnerships, bursaries, training programs)
  • 5% wage spend automation
  • Certification repository

Month 2: LED Intelligence & Employee Welfare Monitoring

Section titled “Month 2: LED Intelligence & Employee Welfare Monitoring”

Week 5-6: Local Economic Development Intelligence

  • Build supplier management system (34+ local suppliers tracked)
  • Implement procurement analytics (spend by supplier, HDSA status, proximity within 50km)
  • Create supplier quality scoring (100-point algorithm - SACE-proven model)
  • Build job creation tracking (direct + indirect employment metrics)
  • Implement business development support program management

Week 7-8: Employee Welfare Monitoring

  • Build safety performance tracking (LTI rates, near-miss reporting, safety training compliance)
  • Implement health program participation tracking (wellness programs, medical screenings)
  • Create wellbeing initiatives dashboard (mental health, employee assistance programs)
  • Build incident management and remediation tracking

Deliverables:

  • LED intelligence module (supplier tracking, procurement analytics, quality scoring)
  • Employee welfare monitoring dashboards
  • Job creation metrics (direct + indirect)

Month 3: GRI 14 Full Compliance & Multi-Award Support

Section titled “Month 3: GRI 14 Full Compliance & Multi-Award Support”

Week 9-10: GRI 14: Mining Sector 2024 Full Compliance

  • Expand GRI 14 from 8-10 topics (pilot) to full 25 material topics
  • Implement emissions reporting (Scope 1, 2, 3 - data integration needed)
  • Build water usage disaggregation dashboards
  • Create waste and tailings management tracking
  • Implement biodiversity impact assessment framework
  • Build closure and rehabilitation planning documentation
  • Ready for 2026 implementation deadline (investor expectations)

Week 11-12: Multi-Award Submission Support

  • Expand Mining Indaba support (add Labour Award, Transparency Award templates)
  • Build Ernst & Young Excellence in Integrated Reporting submission support
  • Create JSE Social Responsibility Index qualification application templates
  • Implement MSCI ESG rating improvement tracking and evidence compilation
  • Build award calendar management (deadlines, requirements, submission tracking)

Deliverables:

  • GRI 14 full compliance (25 material topics)
  • Multi-award submission builder (Mining Indaba 3 categories, EY, JSE SRI, MSCI ESG)
  • Award calendar management system

Month 4: Multi-Stakeholder Portals & Final Deployment

Section titled “Month 4: Multi-Stakeholder Portals & Final Deployment”

Week 13-14: Multi-Stakeholder Portal Access

  • Build community portal (public-facing transparency) - expand from pilot
  • Create employee portal (internal impact visibility, program enrollment)
  • Implement municipality portal (shared dashboards for IDP alignment)
  • Build union portal (consultation records, skills development visibility)
  • Create investor portal (ESG data room for due diligence)

Week 15-16: Advanced Analytics & Production Launch

  • Deploy ML-powered risk prediction (identify SLP compliance gaps 6-12 months ahead)
  • Implement beneficiary impact modeling (ROI on community investments)
  • Build benchmark dashboards (vs. mining industry peers: Anglo American, Exxaro, etc.)
  • Conduct comprehensive UAT across all production modules
  • Executive training on full platform
  • Production deployment (all modules)
  • Organization-wide launch
  • Project handover and support transition

Deliverables:

  • Multi-stakeholder portal access (5 portals: community, employee, municipality, union, investor)
  • Advanced analytics (ML risk prediction, impact modeling, benchmarking)
  • Full platform production deployment
  • Complete documentation and training

MilestoneWeekDeliverablesPayment
Project KickoffWeek 1Charter, plan, team mobilized, pilot optimization20% (R300K-R400K)
Phase 1 CompleteWeek 4Skills development, LED intelligence30% (R450K-R600K)
Phase 2 CompleteWeek 8GRI 14 full compliance, employee welfare30% (R450K-R600K)
Production LaunchWeek 16Multi-award support, multi-stakeholder portals, advanced analytics, training, handover20% (R300K-R400K)

RoleResponsibilitiesAllocation
Project ManagerOverall delivery, stakeholder management, risk mitigation, Mining Indaba coordination50-75%
Technical LeadArchitecture, technical decisions, quality assurance, mining sector expertise75-100%
Backend DeveloperFastAPI, PostgreSQL, ML models, APIs, PDF generation100%
Frontend DeveloperNext.js, dashboards, public portal, UI/UX100%
Data EngineerETL, data migration, evidence file indexing, data quality50-75%
QA EngineerTesting, bug tracking, UAT support50%
RoleResponsibilitiesTime Commitment
Executive SponsorBudget approval, escalation resolution, strategic direction, Mining Indaba champion3-5 hours/week
Project LeadDay-to-day coordination, requirement clarification, UAT, Mining Indaba submission refinement10-15 hours/week
Community Relations TeamMetric definitions, data validation, feedback, UAT, beneficiary tracking, evidence collection5-10 hours/week
ESG/Sustainability ManagerGRI 14 guidance, investor communications, ESG rating coordination3-5 hours/week
IT Team (if applicable)Data access, integration support, security review (POPIA compliance)2-5 hours/week

RiskProbabilityImpactMitigation
Mining Indaba deadline missMediumHighStart pilot by end of January 2025; flag timeline issues early; prioritize submission builder in Week 6
Historical data quality issuesHighMediumValidate data during Week 2 migration; accept gaps for pilot; flag missing evidence early
Community Relations team bandwidthMediumMediumLimit time requirement to 5-10 hrs/week; automate data entry where possible; iSu does heavy lifting in Weeks 1-6
Stakeholder availabilityMediumHighSchedule CEO/Chairman meetings early; establish backup contacts; async communication where possible
Scope creepMediumHighChange control process (documented requests, impact assessment); prioritize ruthlessly (Mining Indaba first)
POPIA/Security concernsLowHighEarly security review (if required); POPIA documentation provided; Hetzner Cape Town hosting (SA data residency)
GRI 14 data gapsMediumMediumAccept partial GRI 14 in pilot (8-10 topics); expand to full 25 topics in production; flag data collection needs early
User adoptionLowHighEarly Community Relations involvement; comprehensive training; CEO/Chairman executive sponsorship
  1. Request: Sepfluor submits change request (email or form)
  2. Assessment: iSu evaluates impact (scope, timeline, cost, Mining Indaba deadline impact)
  3. Proposal: iSu provides change proposal with revised estimates
  4. Approval: Sepfluor Project Lead (Community Relations or CEO/Chairman) approves or rejects
  5. Implementation: Approved changes added to backlog (prioritized based on Mining Indaba urgency)
  6. Documentation: Change logged in project documentation

Critical Path Protection: Changes that risk Mining Indaba 2026 deadline (September 2025) will be flagged and deprioritized unless CEO/Chairman explicitly approves delay.


MetricTargetMeasurement Method
SLP reporting time reduction70%+Compare hours before/after (30 hrs/month → <10 hrs/month)
DMRE audit trail completeness100%Verify all 5 focus areas have complete evidence records
Mining Indaba submission completeness90%+Community Engagement Award submission 90%+ complete (ready for refinement)
Stakeholder communications published4+Community newsletter, investor briefing, employee impact, DMRE report generated
Dashboard load time<3 secondsPerformance monitoring (SLP compliance dashboard)
API response time<200msPerformance monitoring
Stakeholder satisfaction90%+Post-launch survey (CEO, Chairman, Community Relations, ESG Manager)
System uptime99.5%+Monitoring dashboard
MetricTargetMeasurement Method
GRI 14 compliance100% of 25 topics addressedAudit GRI 14 dashboard coverage
Multi-award readiness3+ Mining Indaba submissions completedCommunity Engagement, Labour, Transparency awards 90%+ complete
Skills development compliance100% tracking of 5% wage targetAutomated compliance monitoring validated
LED supplier tracking100% of 34+ suppliers profiledSupplier database completeness
Multi-stakeholder portal adoption5 portals operationalCommunity, employee, municipality, union, investor portals launched

Post-Implementation: Ongoing Support & Expansion

Section titled “Post-Implementation: Ongoing Support & Expansion”

Annual Support Fee: R300K-R400K/year (monthly: R25K-R33K)

Included:

  • Bug fixes and issue resolution
  • Performance monitoring and optimization
  • Security patches and updates (POPIA compliance, vulnerability scanning)
  • Quarterly feature releases (new GRI 14 topics, award template updates)
  • User support (email, video call)
  • Uptime SLA (99.5%)
  • Mining Indaba submission support (annual - September deadline assistance)

Response Times:

  • Critical (system down): 30-minute response, 4-hour resolution target
  • High (feature broken, Mining Indaba submission issue): 2-hour response, 24-hour resolution target
  • Medium (usability issue): 4-hour response, 48-hour resolution target
  • Low (enhancement request): 1-business-day response, quarterly release cycle
ModuleTimelineInvestmentValue
Wiltin Deposit Expansion Support6-8 weeksR300K-R400KPre-development SLP planning, community baseline, impact forecasting
Wallmannsthal Feasibility Support6-8 weeksR250K-R350KCommunity baseline assessment, stakeholder mapping, best practice transfer
Predictive Community Impact Modeling8-12 weeksR250K-R300KML-powered scenario planning (“What if we invest R1M in education vs. healthcare?”)
Industry Benchmark Dashboard4-6 weeksR180K-R220KFluorspar sector peer comparison (if data available), mining ESG benchmarks
Community Digital Engagement Platform8-10 weeksR200K-R250KTwo-way communication (not just reporting), community feedback loops, participatory program design
Investor Relations Automation4-6 weeksR150K-R180KReal-time ESG data room, quarterly briefings auto-generated, sustainability-linked financing support

NameRoleEmailPhone
Nhlanhla MnyanduOperations Director (Executive Sponsor)nhlanhla@isutech.co.za[TBA]
SibongaTechnical Leadsupport@isutech.co.za[TBA]
[TBA]Project Manager[TBA][TBA]
NameRoleEmailPhone
Hendrik SnymanCEO (Executive Sponsor - probable)[TBA]+27 12 622 9400 (corporate)
Dr. Lelau MohubaChairman (Executive Sponsor - probable)[TBA]+27 12 622 9400 (corporate)
Jolandi NelGeneral Enquiries (Initial Contact)info@sepfluor.co.za+27 12 622 9400
[TBA]Community Relations Lead (Project Lead - likely)[TBA][TBA]
[TBA]ESG/Sustainability Manager (Key Stakeholder)[TBA][TBA]

Frequency: Bi-weekly (or as needed during critical phases: Week 5 stakeholder review, Week 8 UAT, Week 10 launch) Attendees: Executive sponsors (CEO/Chairman), project leads (Community Relations, iSu Project Manager) Agenda: Progress review, risk escalation, key decisions (Mining Indaba strategy, production expansion approval)

Frequency: Weekly Attendees: Project managers (iSu + Sepfluor Community Relations Lead), technical leads Agenda: Milestone progress, blockers, upcoming activities, data collection needs

Frequency: Daily (during development phases: Weeks 2-8) Attendees: Development team (iSu) Agenda: Yesterday’s progress, today’s plan, blockers

  • Formal Communication: Email (project milestones, change requests, escalations, Mining Indaba strategy)
  • Day-to-Day: WhatsApp / Microsoft Teams / Slack (quick questions, data requests, evidence file transfers)
  • Documentation: Shared drive (deliverables, meeting notes, project documents, Mining Indaba drafts)

Document Version: 1.0 Last Updated: 20/11/2025 Owner: iSu Technologies Sales Team Status: Ready for Sepfluor Engagement


This implementation roadmap will be refined during the discovery phase (Week 1) to account for Sepfluor-specific requirements, data sources (historical SLP records), and Mining Indaba award strategy. Timelines are estimates based on similar implementations (MGSLG: 5 weeks, SACE: 5 weeks, 85% code reuse) and may be adjusted during planning. Critical constraint: Mining Indaba 2026 submissions open June 2025, deadline September 2025 - pilot must start by end of January 2025 to maximize award potential.