NSTF - Implementation Roadmap
NSTF Implementation Roadmap
Section titled “NSTF Implementation Roadmap”Delivery Options Overview
Section titled “Delivery Options Overview”| Option | Duration | Key Milestones | Go-Live Target |
|---|---|---|---|
| Pilot (MVP) | 8 weeks | 4 sprints | Q1 2025 |
| Comprehensive Awards | 12 weeks | 6 sprints | Q2 2025 (ready for Nov 2025 cycle) |
| Full Ecosystem | 26 weeks | 3 phases | Q3 2025 |
Option A: Awards Management Pilot (8 Weeks)
Section titled “Option A: Awards Management Pilot (8 Weeks)”Week 1-2: Discovery & Design Sprint
Section titled “Week 1-2: Discovery & Design Sprint”Objectives:
- Finalize requirements
- Design user workflows
- Plan technical architecture
Activities:
- Kickoff meeting (stakeholders, project team)
- Requirements workshop (2-3 hours)
- User story mapping (nominators, adjudicators, admins)
- Technical design document
- UI/UX wireframes
Deliverables:
- ✅ Requirements document signed off
- ✅ Technical architecture diagram
- ✅ UI wireframes approved
- ✅ Sprint backlog created
NSTF Involvement: 4-6 hours (workshops and approvals)
Week 3-4: Sprint 1 - Core Platform Build
Section titled “Week 3-4: Sprint 1 - Core Platform Build”Objectives:
- Build nomination submission portal
- Basic admin dashboard
Features Delivered:
- Nomination form (category selection, nominee info, motivation text)
- File upload system
- Confirmation emails
- Admin view (list all nominations)
Deliverables:
- ✅ Working nomination portal (demo-ready)
- ✅ Basic admin dashboard
NSTF Involvement: 1-2 hours (weekly demo and feedback)
Week 5-6: Sprint 2 - Adjudication & Workflows
Section titled “Week 5-6: Sprint 2 - Adjudication & Workflows”Objectives:
- Adjudicator review interface
- Scoring and evaluation tools
Features Delivered:
- Panel member login
- Nomination assignment to adjudicators
- Scoring rubric interface
- Review submission and tracking
Deliverables:
- ✅ Adjudicator portal functional
- ✅ End-to-end workflow (nominate → review → score)
NSTF Involvement: 2-3 hours (test adjudicator interface, provide feedback)
Week 7: Sprint 3 - Integration & Testing
Section titled “Week 7: Sprint 3 - Integration & Testing”Objectives:
- Integrate with NSTF database
- Connect to Everlytic
- User acceptance testing
Features Delivered:
- Database integration (nominee data sync)
- Email automation (via Everlytic)
- Bug fixes and refinements
Deliverables:
- ✅ Integrated platform ready for UAT
- ✅ Test plan and test cases
NSTF Involvement: 4-6 hours (user acceptance testing)
Week 8: Training & Go-Live
Section titled “Week 8: Training & Go-Live”Objectives:
- Train NSTF team
- Deploy to production
- Launch support
Activities:
- Administrator training (2-hour session)
- User documentation delivery
- Production deployment
- Launch announcement
- 30-day support period begins
Deliverables:
- ✅ Platform live and operational
- ✅ NSTF team trained
- ✅ Documentation provided
- ✅ Support hotline active
NSTF Involvement: 3-4 hours (training session and launch coordination)
PAYMENT MILESTONE: Final 20% payment due
Option B: Comprehensive Awards System (12 Weeks)
Section titled “Option B: Comprehensive Awards System (12 Weeks)”Phase 1: Foundation (Weeks 1-4)
Section titled “Phase 1: Foundation (Weeks 1-4)”Same as Pilot Sprint 1-2, but with additional advanced features
Additional Features:
- Multi-stage workflow configuration
- Advanced admin controls
- Historical data import preparation
PAYMENT MILESTONE: 30% payment (after Week 4)
Phase 2: Advanced Features (Weeks 5-8)
Section titled “Phase 2: Advanced Features (Weeks 5-8)”Objectives:
- Analytics and reporting
- Advanced automation
- Full Everlytic integration
Features Delivered:
- Dashboard analytics (diversity metrics, submission trends, geography maps)
- Automated email workflows (reminders, status updates, winner announcements)
- Adjudicator collaboration tools (comments, discussions)
- Winner showcase page (public-facing)
- Historical nominee/winner archive
Deliverables:
- ✅ Analytics dashboard operational
- ✅ Email automation configured
- ✅ Collaboration features active
NSTF Involvement: 3-4 hours/week (review demos, test features)
PAYMENT MILESTONE: 35% payment (after Week 8)
Phase 3: Testing, Training & Launch (Weeks 9-12)
Section titled “Phase 3: Testing, Training & Launch (Weeks 9-12)”Week 9-10: Comprehensive Testing
- Functional testing (all features)
- Performance testing (load testing with 500+ concurrent users)
- Security testing (penetration test, POPIA compliance audit)
- User acceptance testing (NSTF team + pilot users)
Week 11: Training
- Nominator orientation webinar (1 hour, recorded)
- Adjudicator training session (1.5 hours, recorded)
- Administrator deep-dive training (3 hours, hands-on)
- Help desk training for NSTF support staff
Week 12: Production Launch
- Data migration (historical nominees and winners)
- Production deployment
- Launch communications (eNews announcement, website update)
- 90-day support period begins
Deliverables:
- ✅ Platform fully operational
- ✅ All stakeholders trained
- ✅ Documentation complete
- ✅ Support channels active
NSTF Involvement: 8-12 hours (testing, training, launch coordination)
PAYMENT MILESTONE: Final 35% payment (after Week 12)
Option C: Full Ecosystem Platform (26 Weeks / 6 Months)
Section titled “Option C: Full Ecosystem Platform (26 Weeks / 6 Months)”Phase 1: Awards System (Weeks 1-12)
Section titled “Phase 1: Awards System (Weeks 1-12)”Same as Option B - Comprehensive Awards
Payment: 40% of total ecosystem investment
Phase 2: Event Management System (Weeks 13-20)
Section titled “Phase 2: Event Management System (Weeks 13-20)”Weeks 13-14: Discovery & Design
- Map NSTF event types (discussion forums, AGM, awards ceremony)
- Design registration workflows
- Plan Zoom/Teams integration
Weeks 15-18: Development
- Event creation and management interface
- Registration portal (public-facing)
- Attendance tracking
- Certificate generation
- Post-event surveys
- Integration with discussion forum calendar
Weeks 19-20: Testing & Training
- Pilot with next discussion forum
- Train events team
- Refine based on feedback
Deliverables:
- ✅ Event management platform operational
- ✅ Integrated with awards system (shared member database)
- ✅ First event successfully managed on platform
NSTF Involvement: 6-8 hours (workshops, testing, training)
PAYMENT MILESTONE: 30% payment (after Week 20)
Phase 3: Membership Portal (Weeks 21-26)
Section titled “Phase 3: Membership Portal (Weeks 21-26)”Weeks 21-22: Membership Design
- Map 6 membership sectors
- Design tiered membership structure
- Benefits tracking requirements
Weeks 23-25: Development
- Member self-service portal (registration, renewal, profile management)
- Payment processing integration
- Member directory (searchable, filterable)
- Benefits tracking dashboard
- Newsletter submission portal (for member news/events)
- Integration with awards and events (single sign-on)
Week 26: Launch & Training
- Soft launch to existing members (invite to create accounts)
- Administrator training
- Member onboarding communications
Deliverables:
- ✅ Membership portal live
- ✅ Integrated ecosystem (awards + events + membership)
- ✅ Unified analytics dashboard
- ✅ 100+ members can access single platform
NSTF Involvement: 8-10 hours (testing, training, member communications)
PAYMENT MILESTONE: Final 30% payment (after Week 26)
Critical Success Factors
Section titled “Critical Success Factors”1. NSTF Availability & Engagement
Section titled “1. NSTF Availability & Engagement”Required:
- Executive sponsor assigned (weekly check-ins)
- Awards Manager available for workshops and testing (4-6 hours/week during active phases)
- Subject matter experts accessible (adjudicators, past nominators for user testing)
If NSTF Can’t Commit:
- Timeline extends (delays while waiting for approvals/feedback)
- Quality suffers (assumptions made without NSTF input)
2. Decision-Making Speed
Section titled “2. Decision-Making Speed”Critical Decision Points:
- Week 2: Approve requirements and design
- Week 4 (Pilot) / Week 8 (Comprehensive): Approve UAT and proceed to launch
- Phase transitions (Option C): Approve completion before starting next phase
SLA: NSTF provides feedback/approvals within 3 business days (or timeline extends)
3. Data Readiness
Section titled “3. Data Readiness”Required from NSTF:
- Historical nominee/winner data (if importing)
- Awards category definitions
- Adjudicator panel details
- Everlytic account access (for integration)
- NSTF database schema (for integration)
Timeline Impact: Delays in data provision = delays in integration testing
4. Change Management
Section titled “4. Change Management”NSTF Responsibilities:
- Communicate platform launch to stakeholders (nominators, adjudicators, members)
- Manage expectations (new process, training required)
- Provide first-line support (iSu handles escalations)
iSu Support:
- Communications templates provided
- Video tutorials for self-service support
- Help desk during critical periods
Risk Management & Contingency
Section titled “Risk Management & Contingency”Risk 1: Scope Creep
Section titled “Risk 1: Scope Creep”Mitigation:
- Fixed scope in contract (changes = change request process)
- Weekly demos (catch scope drift early)
- Change approval process (NSTF signs off on additions, timeline/cost impact disclosed)
Risk 2: Technical Delays
Section titled “Risk 2: Technical Delays”Mitigation:
- Buffer time in estimates (12-week plan has 2-week buffer)
- Agile delivery (working software every 2 weeks, not all-or-nothing at end)
- Escalation process (if blocker, executive sponsors engage immediately)
Risk 3: User Adoption Failure
Section titled “Risk 3: User Adoption Failure”Mitigation:
- User testing during development (catch usability issues early)
- Training and documentation (reduce friction)
- Support during first cycle (hand-holding for early adopters)
- Feedback loop (continuous improvement post-launch)
Risk 4: Integration Challenges
Section titled “Risk 4: Integration Challenges”Mitigation:
- API testing in Week 1 (validate Everlytic, database access early)
- Fallback options (if integration fails, manual workarounds available)
- Dedicated integration sprint (Week 7 in Pilot, Weeks 9-10 in Comprehensive)
Post-Launch: Continuous Improvement
Section titled “Post-Launch: Continuous Improvement”30-Day Post-Launch Review
Section titled “30-Day Post-Launch Review”- User satisfaction survey (nominators, adjudicators, admins)
- Platform analytics review (usage patterns, drop-off points, errors)
- Feedback collection (what’s working, what needs improvement)
- Prioritize enhancements for next release
90-Day Optimization
Section titled “90-Day Optimization”- Implement top-requested features
- Performance tuning based on real usage data
- Documentation updates
- Training refreshers if needed
Annual Major Update
Section titled “Annual Major Update”- New features based on year’s learnings
- Security and compliance updates
- Platform modernization (UI refresh, technology upgrades)
Success Metrics
Section titled “Success Metrics”Platform Performance
Section titled “Platform Performance”- ✅ 99.5%+ uptime during awards cycle
- ✅ <2 second page load times
- ✅ Zero data loss incidents
User Satisfaction
Section titled “User Satisfaction”- ✅ 85%+ nominator satisfaction (post-awards survey)
- ✅ 90%+ adjudicator satisfaction
- ✅ 95%+ admin satisfaction (NSTF team)
Efficiency Gains
Section titled “Efficiency Gains”- ✅ 60-70% reduction in admin time (measured pre/post)
- ✅ 50%+ reduction in support inquiries (“where’s my nomination?”)
- ✅ 100% elimination of manual data entry errors
Adoption
Section titled “Adoption”- ✅ 95%+ nomination completion rate (started but not submitted <5%)
- ✅ 100% adjudicator panel participation (all assigned reviews completed)
- ✅ 80%+ positive feedback from nominators
Next Steps
Section titled “Next Steps”To Initiate Project:
- Select implementation option (Pilot, Comprehensive, or Full Ecosystem)
- Sign contract and SOW
- Assign NSTF project team (sponsor, manager, SMEs)
- Schedule kickoff meeting (Week 1, Day 1)
- Provide data and system access to iSu team
- Begin sprint planning
Target Start Date: [To be determined based on NSTF decision timeline] Target Go-Live:
- Pilot: 8 weeks from start
- Comprehensive: 12 weeks from start (Q2 2025 for Nov 2025 cycle)
- Full Ecosystem: 26 weeks from start
Roadmap Owner: iSu Technologies Delivery Team + NSTF Project Sponsor Last Updated: December 2, 2025 Next Review: Weekly during active project, monthly post-launch