NSTF - Implementation Roadmap

OptionDurationKey MilestonesGo-Live Target
Pilot (MVP)8 weeks4 sprintsQ1 2025
Comprehensive Awards12 weeks6 sprintsQ2 2025 (ready for Nov 2025 cycle)
Full Ecosystem26 weeks3 phasesQ3 2025

Option A: Awards Management Pilot (8 Weeks)

Section titled “Option A: Awards Management Pilot (8 Weeks)”

Objectives:

  • Finalize requirements
  • Design user workflows
  • Plan technical architecture

Activities:

  • Kickoff meeting (stakeholders, project team)
  • Requirements workshop (2-3 hours)
  • User story mapping (nominators, adjudicators, admins)
  • Technical design document
  • UI/UX wireframes

Deliverables:

  • ✅ Requirements document signed off
  • ✅ Technical architecture diagram
  • ✅ UI wireframes approved
  • ✅ Sprint backlog created

NSTF Involvement: 4-6 hours (workshops and approvals)


Objectives:

  • Build nomination submission portal
  • Basic admin dashboard

Features Delivered:

  • Nomination form (category selection, nominee info, motivation text)
  • File upload system
  • Confirmation emails
  • Admin view (list all nominations)

Deliverables:

  • ✅ Working nomination portal (demo-ready)
  • ✅ Basic admin dashboard

NSTF Involvement: 1-2 hours (weekly demo and feedback)


Week 5-6: Sprint 2 - Adjudication & Workflows

Section titled “Week 5-6: Sprint 2 - Adjudication & Workflows”

Objectives:

  • Adjudicator review interface
  • Scoring and evaluation tools

Features Delivered:

  • Panel member login
  • Nomination assignment to adjudicators
  • Scoring rubric interface
  • Review submission and tracking

Deliverables:

  • ✅ Adjudicator portal functional
  • ✅ End-to-end workflow (nominate → review → score)

NSTF Involvement: 2-3 hours (test adjudicator interface, provide feedback)


Objectives:

  • Integrate with NSTF database
  • Connect to Everlytic
  • User acceptance testing

Features Delivered:

  • Database integration (nominee data sync)
  • Email automation (via Everlytic)
  • Bug fixes and refinements

Deliverables:

  • ✅ Integrated platform ready for UAT
  • ✅ Test plan and test cases

NSTF Involvement: 4-6 hours (user acceptance testing)


Objectives:

  • Train NSTF team
  • Deploy to production
  • Launch support

Activities:

  • Administrator training (2-hour session)
  • User documentation delivery
  • Production deployment
  • Launch announcement
  • 30-day support period begins

Deliverables:

  • ✅ Platform live and operational
  • ✅ NSTF team trained
  • ✅ Documentation provided
  • ✅ Support hotline active

NSTF Involvement: 3-4 hours (training session and launch coordination)

PAYMENT MILESTONE: Final 20% payment due


Option B: Comprehensive Awards System (12 Weeks)

Section titled “Option B: Comprehensive Awards System (12 Weeks)”

Same as Pilot Sprint 1-2, but with additional advanced features

Additional Features:

  • Multi-stage workflow configuration
  • Advanced admin controls
  • Historical data import preparation

PAYMENT MILESTONE: 30% payment (after Week 4)


Objectives:

  • Analytics and reporting
  • Advanced automation
  • Full Everlytic integration

Features Delivered:

  • Dashboard analytics (diversity metrics, submission trends, geography maps)
  • Automated email workflows (reminders, status updates, winner announcements)
  • Adjudicator collaboration tools (comments, discussions)
  • Winner showcase page (public-facing)
  • Historical nominee/winner archive

Deliverables:

  • ✅ Analytics dashboard operational
  • ✅ Email automation configured
  • ✅ Collaboration features active

NSTF Involvement: 3-4 hours/week (review demos, test features)

PAYMENT MILESTONE: 35% payment (after Week 8)


Phase 3: Testing, Training & Launch (Weeks 9-12)

Section titled “Phase 3: Testing, Training & Launch (Weeks 9-12)”

Week 9-10: Comprehensive Testing

  • Functional testing (all features)
  • Performance testing (load testing with 500+ concurrent users)
  • Security testing (penetration test, POPIA compliance audit)
  • User acceptance testing (NSTF team + pilot users)

Week 11: Training

  • Nominator orientation webinar (1 hour, recorded)
  • Adjudicator training session (1.5 hours, recorded)
  • Administrator deep-dive training (3 hours, hands-on)
  • Help desk training for NSTF support staff

Week 12: Production Launch

  • Data migration (historical nominees and winners)
  • Production deployment
  • Launch communications (eNews announcement, website update)
  • 90-day support period begins

Deliverables:

  • ✅ Platform fully operational
  • ✅ All stakeholders trained
  • ✅ Documentation complete
  • ✅ Support channels active

NSTF Involvement: 8-12 hours (testing, training, launch coordination)

PAYMENT MILESTONE: Final 35% payment (after Week 12)


Option C: Full Ecosystem Platform (26 Weeks / 6 Months)

Section titled “Option C: Full Ecosystem Platform (26 Weeks / 6 Months)”

Same as Option B - Comprehensive Awards

Payment: 40% of total ecosystem investment


Phase 2: Event Management System (Weeks 13-20)

Section titled “Phase 2: Event Management System (Weeks 13-20)”

Weeks 13-14: Discovery & Design

  • Map NSTF event types (discussion forums, AGM, awards ceremony)
  • Design registration workflows
  • Plan Zoom/Teams integration

Weeks 15-18: Development

  • Event creation and management interface
  • Registration portal (public-facing)
  • Attendance tracking
  • Certificate generation
  • Post-event surveys
  • Integration with discussion forum calendar

Weeks 19-20: Testing & Training

  • Pilot with next discussion forum
  • Train events team
  • Refine based on feedback

Deliverables:

  • ✅ Event management platform operational
  • ✅ Integrated with awards system (shared member database)
  • ✅ First event successfully managed on platform

NSTF Involvement: 6-8 hours (workshops, testing, training)

PAYMENT MILESTONE: 30% payment (after Week 20)


Weeks 21-22: Membership Design

  • Map 6 membership sectors
  • Design tiered membership structure
  • Benefits tracking requirements

Weeks 23-25: Development

  • Member self-service portal (registration, renewal, profile management)
  • Payment processing integration
  • Member directory (searchable, filterable)
  • Benefits tracking dashboard
  • Newsletter submission portal (for member news/events)
  • Integration with awards and events (single sign-on)

Week 26: Launch & Training

  • Soft launch to existing members (invite to create accounts)
  • Administrator training
  • Member onboarding communications

Deliverables:

  • ✅ Membership portal live
  • ✅ Integrated ecosystem (awards + events + membership)
  • ✅ Unified analytics dashboard
  • ✅ 100+ members can access single platform

NSTF Involvement: 8-10 hours (testing, training, member communications)

PAYMENT MILESTONE: Final 30% payment (after Week 26)


Required:

  • Executive sponsor assigned (weekly check-ins)
  • Awards Manager available for workshops and testing (4-6 hours/week during active phases)
  • Subject matter experts accessible (adjudicators, past nominators for user testing)

If NSTF Can’t Commit:

  • Timeline extends (delays while waiting for approvals/feedback)
  • Quality suffers (assumptions made without NSTF input)

Critical Decision Points:

  • Week 2: Approve requirements and design
  • Week 4 (Pilot) / Week 8 (Comprehensive): Approve UAT and proceed to launch
  • Phase transitions (Option C): Approve completion before starting next phase

SLA: NSTF provides feedback/approvals within 3 business days (or timeline extends)


Required from NSTF:

  • Historical nominee/winner data (if importing)
  • Awards category definitions
  • Adjudicator panel details
  • Everlytic account access (for integration)
  • NSTF database schema (for integration)

Timeline Impact: Delays in data provision = delays in integration testing


NSTF Responsibilities:

  • Communicate platform launch to stakeholders (nominators, adjudicators, members)
  • Manage expectations (new process, training required)
  • Provide first-line support (iSu handles escalations)

iSu Support:

  • Communications templates provided
  • Video tutorials for self-service support
  • Help desk during critical periods

Mitigation:

  • Fixed scope in contract (changes = change request process)
  • Weekly demos (catch scope drift early)
  • Change approval process (NSTF signs off on additions, timeline/cost impact disclosed)

Mitigation:

  • Buffer time in estimates (12-week plan has 2-week buffer)
  • Agile delivery (working software every 2 weeks, not all-or-nothing at end)
  • Escalation process (if blocker, executive sponsors engage immediately)

Mitigation:

  • User testing during development (catch usability issues early)
  • Training and documentation (reduce friction)
  • Support during first cycle (hand-holding for early adopters)
  • Feedback loop (continuous improvement post-launch)

Mitigation:

  • API testing in Week 1 (validate Everlytic, database access early)
  • Fallback options (if integration fails, manual workarounds available)
  • Dedicated integration sprint (Week 7 in Pilot, Weeks 9-10 in Comprehensive)

  • User satisfaction survey (nominators, adjudicators, admins)
  • Platform analytics review (usage patterns, drop-off points, errors)
  • Feedback collection (what’s working, what needs improvement)
  • Prioritize enhancements for next release
  • Implement top-requested features
  • Performance tuning based on real usage data
  • Documentation updates
  • Training refreshers if needed
  • New features based on year’s learnings
  • Security and compliance updates
  • Platform modernization (UI refresh, technology upgrades)

  • ✅ 99.5%+ uptime during awards cycle
  • ✅ <2 second page load times
  • ✅ Zero data loss incidents
  • ✅ 85%+ nominator satisfaction (post-awards survey)
  • ✅ 90%+ adjudicator satisfaction
  • ✅ 95%+ admin satisfaction (NSTF team)
  • ✅ 60-70% reduction in admin time (measured pre/post)
  • ✅ 50%+ reduction in support inquiries (“where’s my nomination?”)
  • ✅ 100% elimination of manual data entry errors
  • ✅ 95%+ nomination completion rate (started but not submitted <5%)
  • ✅ 100% adjudicator panel participation (all assigned reviews completed)
  • ✅ 80%+ positive feedback from nominators

To Initiate Project:

  1. Select implementation option (Pilot, Comprehensive, or Full Ecosystem)
  2. Sign contract and SOW
  3. Assign NSTF project team (sponsor, manager, SMEs)
  4. Schedule kickoff meeting (Week 1, Day 1)
  5. Provide data and system access to iSu team
  6. Begin sprint planning

Target Start Date: [To be determined based on NSTF decision timeline] Target Go-Live:

  • Pilot: 8 weeks from start
  • Comprehensive: 12 weeks from start (Q2 2025 for Nov 2025 cycle)
  • Full Ecosystem: 26 weeks from start

Roadmap Owner: iSu Technologies Delivery Team + NSTF Project Sponsor Last Updated: December 2, 2025 Next Review: Weekly during active project, monthly post-launch